Building a Private School in Turkey: Ministry Standards, Process and Timeline (2026)

Published: 4 min readÇET Yapı Editorial Team
TED Üsküdar College Campus, built by ÇET Yapı
In short
  • Under MEB rules, a classroom in a primary, middle or high school must be at least 20 m², with at least 1.5 m² of usable area per pupil.
  • A primary school needs a playground of at least 500 m² suitable for ceremonies plus 2 m² per pupil, a library of at least 30 m² and an indoor PE hall of at least 80 m².
  • A school may only open in a building with at least as many classrooms as grade years; kindergarten classrooms need at least 15 m² and 1.5 m² of play area per child.
  • Under the 2018 Turkish Building Earthquake Code, schools are designed with the highest importance factor (I = 1.5).
  • ÇET Yapı has built more than 15 educational buildings for TED, Doğa, Okyanus, Bahçeşehir and Vega schools.

In a private school investment, the building determines everything from the opening licence to the pupils' daily experience. Since 2010, ÇET Yapı has built more than 15 educational buildings for TED, Doğa, Okyanus, Bahçeşehir and Vega schools in Istanbul, Ankara, İzmir, Kayseri and Hatay. This guide summarises the current standards of Turkey's Ministry of National Education (MEB) and a school building's journey from land to opening.

Key dimensions under MEB standards

The physical requirements for private schools are set by the Standards Directive for Private Educational Institutions (this article uses the consolidated text dated 27.11.2025). The most decisive figures for design are:

Criterion Primary / Middle / High school Kindergarten
Minimum classroom area 20 m² 15 m²
Usable area per pupil in classrooms at least 1.5 m² —
Playground at least 500 m² suitable for ceremonies, plus 2 m² per pupil 1.5 m² of play area per child
Library (primary school) at least 30 m² bookshelf
Indoor PE hall (primary school) at least 80 m² —
Music and visual arts room 1.5 m² per pupil —
Head teacher's office — at least 10 m²

In addition:

  • A school may only open in a building with at least as many classrooms as grade years (e.g. at least 4 classrooms for a primary school).
  • Laboratories require at least 1.5 m² per pupil.
  • Accessibility ramps may not exceed a 6% slope, and buildings must comply with the Regulation on Fire Protection of Buildings.

Rule of thumb: a class of 24 needs 24 × 1.5 = 36 m². The 20 m² minimum only governs small groups.

Seismic safety: schools are in the highest importance class

The 2018 Turkish Building Earthquake Code (TBDY) counts schools among buildings where people stay for long periods in large numbers and sets the building importance factor at I = 1.5. This means designing for higher seismic forces than for a residential building of the same size on the same soil, which makes the geotechnical survey, structural design and independent building inspection especially critical.

From land to opening: the process

  1. Land and zoning: the parcel must be zoned for educational use. Because of the playground requirement, plot size must be considered together with pupil capacity.
  2. Capacity and feasibility: target pupils → number of classrooms → gross floor area → playground requirement.
  3. Architectural design: MEB standards, fire regulations, accessibility and the earthquake code are resolved together; shared spaces such as the conference hall, sports hall, laboratories and dining hall are sized.
  4. Building permit and inspection
  5. Construction: school programmes are planned backwards from the start of the academic year in September.
  6. Occupancy permit and institution licence: after completion, the owner applies to the provincial directorate of national education; the building is inspected against the standards using the layout plan.

Figures from completed projects

Some school campuses completed by ÇET Yapı show how different scales are delivered:

Project Total construction area Classrooms Duration
Ankara İncek Okyanus College 17,656 m² 63 + 8 6 months (2015)
Kayseri Doğa College 10,028 m² 67 6 months (2013)
Başakşehir Doğa College 9,388 m² 65 6 months (2013)
Kristalşehir Vega Schools 8,300 m² 27 + 5 8 months (2016)
TED Üsküdar College Campus 19,232.92 m² 85 + 5 (two blocks) 53 months (2018–2022)

What the fast-track projects have in common is that design decisions were frozen before construction started and the school opening date was the contract's main objective.

Five tips for school investors

  • Calculate the playground first: the 2 m² per pupil rule often limits capacity before floor area does.
  • Design flexible classrooms: use modular dimensions that can adapt to changes between levels (kindergarten to high school).
  • Share common facilities: sports and conference halls can be positioned for shared use between levels.
  • Plan backwards from opening day: sequence permit, construction, occupancy and licence against September.
  • Never compromise on seismic safety: in a building with an importance factor of 1.5, structural design and soil investigation are about trust, not cost.

If you would like support from the feasibility stage for your school project, contact the ÇET Yapı team.

Frequently Asked Questions

How large must a classroom be in a Turkish private school?

According to the Standards Directive for Private Educational Institutions, a classroom in a primary, middle or secondary school cannot be smaller than 20 m², and each pupil needs at least 1.5 m² of usable area — so a class of 24 needs at least 36 m².

What are the playground requirements?

Primary, middle and high schools need a playground of at least 500 m² suitable for ceremonies, with 2 m² per pupil. Kindergartens need 1.5 m² of play area per child.

How long does it take to build a school?

It depends on scale and approvals. In ÇET Yapı projects, the 10,028 m² Kayseri Doğa College took about 6 months, the 17,656 m² Ankara İncek Okyanus College 6 months, and the two-block, 19,232 m² TED Üsküdar College Campus 53 months.

How are schools classified under the Turkish earthquake code?

The 2018 Turkish Building Earthquake Code lists schools among buildings where people stay for long periods in large numbers and assigns them the highest building importance factor, I = 1.5.

Can an existing building be converted into a school?

Yes, if it meets MEB standards, fire and seismic safety requirements and the permitted zoning use. Classroom count, playground area and accessibility should be checked first.

Talk to us about your project

We are ready to share the experience we have gained since 1993 in educational buildings, housing, urban transformation and restoration projects.

Contact Us